Trillium Ridge House
Cashiers · 42 Trillium Links Way
For David and Claire Benoit, built by Cody Ramsey and the Sadlon and Associates team
Foundation20% of the build

Decisions waiting on you

SelectionSent 3 days ago

Garage door style and finish

Pick between the full-view glass and the carriage-house wood-clad door for the three-bay garage.

Signing off keeps a record of who approved it and when.

Weekly updates

Wednesday, July 8

Foundation work is underway at Trillium Ridge. Footings are poured on the north wing and the crew is moving to the walls as the weather allows.

  • Progress: North-wing footings poured, clean and true.
  • Heads-up: Watching the forecast, which may shift the inspection a day or two.

1 progress photo attached

Warm regards, Cody and the Sadlon and Associates team

Recent progress

Jul 10
Milestone

Footings poured on the north wing. Clean pour and good consolidation, no cold joints.

The schedule ahead

Footings inspectionJul 14
Foundation wallsJul 21
Waterproofing and perimeter drainJul 28
Backfill and slab prepAug 7
Slab pouredAug 15