Your build
Whiteside Cove Residence
Cashiers · 1187 Whiteside Cove Rd
For Paul and Diane Harlan, built by Wade Hollifield and the Sadlon and Associates team
Dry-in40% of the build

Decisions waiting on you

Change orderSent 2 days ago

Closed-cell foam at the crawlspace band joist

$8,400

Upgrade the band-joist detail to two inches of closed-cell spray foam for a tighter, warmer floor system. Recommended after this week's air-sealing walkthrough.

Signing off keeps a record of who approved it and when.
SelectionSent 4 days ago

Primary bath stone: honed or leathered granite

Choose the finish for the primary bath vanity and surround. Both samples are waiting at the site trailer whenever you are up on the mountain.

Signing off keeps a record of who approved it and when.
On the record
  • Standing-seam metal roof over the porches · $14,200Signed offPaul Harlan · Jun 25
  • Exterior stain colorSigned offDiane Harlan · Jun 17

Weekly updates

Thursday, July 9

A strong week at Whiteside Cove. The framing crew topped out and we started closing in the roof, so the house finally reads at full height against the ridge.

  • Progress: Framing topped out and the ridge beam is set.
  • Progress: Roof sheathing on, ready for the dry-in membrane.
  • Building science: Confirmed the air-sealing sequence with the framer for a tight envelope.

3 progress photos attached

Warm regards, Wade and the Sadlon and Associates team

Thursday, July 2

Framing kept pace with the good weather this week and the main-level walls are all standing. You can walk the great room and feel the volume now.

  • Progress: Main-level walls framed and braced.
  • On site: Set the steel for the great-room ridge.

2 progress photos attached

Warm regards, Wade and the Sadlon and Associates team

Recent progress

Jul 16
Milestone

Good crew day starting. Sheathed and taped the last gable end. The Whiteside face is catching the morning light off the back deck now.

Jul 11
Milestone

Roof is dried-in. Ice-and-water shield down at every eave and valley, synthetic underlayment over the field. The house is weather-tight ahead of the front coming through Thursday.

The schedule ahead

County framing inspectionJul 18
Windows and doors installedJul 25
Mechanical rough-in, HVAC and ERVAug 5
Blower-door pre-drywall testAug 19
DrywallSep 2