Trillium Ridge House
David and Claire Benoit · Foundation
CR
This week's update is due
Plumbline will compile the week below into an owner-ready letter.
Ready to compile·2 field notes·1 photo·1 decision
- Weather delay
Rain all week held the footings inspection. County can not get out until the ground firms up, so I rescheduled and let the Benoits know the slab date moves with it.
Cody · 2 days ago
- Milestone
Footings poured on the north wing. Clean pour and good consolidation, no cold joints.
Cody · 6 days ago · photo attached
Decisions this week
- Garage door style and finishWaiting
The schedule ahead
- Footings inspection (due Jul 14)
- Foundation walls (due Jul 21)
- Waterproofing and perimeter drain (due Jul 28)