Whiteside Cove Residence
Paul and Diane Harlan · Dry-in
WH

This week's update is due

Plumbline will compile the week below into an owner-ready letter.

Ready to compile·6 field notes·2 photos·2 decisions
  • Milestone

    Good crew day starting. Sheathed and taped the last gable end. The Whiteside face is catching the morning light off the back deck now.

    Wade · 11 hr ago · photo attached

  • Inspection

    County framing inspection is set for Wednesday. Punch-listed a few strap-nailing spots for the crew this morning so we pass clean.

    Wade · yesterday

  • Note

    Walked the window openings with the installer ahead of next week. Rough openings all check out against the order.

    Wade · 2 days ago

  • Weather delay

    Marble supplier pushed the primary bath stone about two weeks. Not on the critical path yet, flagging it early so the Harlans hear it from us first.

    Wade · 3 days ago

  • Building science

    Walked the pre-insulation air-sealing plan with the framer. Bottom plates and every band-joist penetration get sealed before rough-in so the envelope tests tight.

    Wade · 4 days ago

  • Milestone

    Roof is dried-in. Ice-and-water shield down at every eave and valley, synthetic underlayment over the field. The house is weather-tight ahead of the front coming through Thursday.

    Wade · 5 days ago · photo attached

Decisions this week
  • Closed-cell foam at the crawlspace band joist$8,400Waiting
  • Primary bath stone: honed or leathered graniteWaiting
The schedule ahead
  • County framing inspection (due Jul 18)
  • Windows and doors installed (due Jul 25)
  • Mechanical rough-in, HVAC and ERV (due Aug 5)