- Milestone
Good crew day starting. Sheathed and taped the last gable end. The Whiteside face is catching the morning light off the back deck now.
Wade · 11 hr ago · photo attached
- Inspection
County framing inspection is set for Wednesday. Punch-listed a few strap-nailing spots for the crew this morning so we pass clean.
Wade · yesterday
- Note
Walked the window openings with the installer ahead of next week. Rough openings all check out against the order.
Wade · 2 days ago
- Weather delay
Marble supplier pushed the primary bath stone about two weeks. Not on the critical path yet, flagging it early so the Harlans hear it from us first.
Wade · 3 days ago
- Building science
Walked the pre-insulation air-sealing plan with the framer. Bottom plates and every band-joist penetration get sealed before rough-in so the envelope tests tight.
Wade · 4 days ago
- Milestone
Roof is dried-in. Ice-and-water shield down at every eave and valley, synthetic underlayment over the field. The house is weather-tight ahead of the front coming through Thursday.
Wade · 5 days ago · photo attached
- Closed-cell foam at the crawlspace band joist$8,400Waiting
- Primary bath stone: honed or leathered graniteWaiting
- County framing inspection (due Jul 18)
- Windows and doors installed (due Jul 25)
- Mechanical rough-in, HVAC and ERV (due Aug 5)